Grants and Contracts Details
Description
KTC will coordinate with KYTC maintenance staff to secure the necessary in-house traffic control to perform the following work items as noted previously in table one and described below: Falling Weight Deflectometer (FWD), Ground Penetrating Radar (GPR), coring, rutting measurements, and pipe inspections.
-Perform FWD testing on 250 ft. intervals, and back calculate sub-grade and existing pavement structure modulus values, and stiffness values.
-Perform GPR testing on approximately one foot intervals to determine pavement and sub-base thickness variation.
-Core pavement structure and hand-dig through sub-base material to sub-grade for verification thicknesses. Identify crack mode (top down/bottom up), and classification of existing sub-base. Additional cores maybe taken to assist with both FWD and GPR data if pavement conditions change dramatically throughout the project.
-Collect rutting measurements at each core location in the right and left wheel path.
Status | Finished |
---|---|
Effective start/end date | 9/25/17 → 6/30/20 |
Funding
- KY Transportation Cabinet: $227,500.00