Abstract
For one-stage production, operations management faces the following three challenges to make decisions, which are inconsistencies between key performance indicators (KPIs) for production, trade-offs between the expected return and the risk in modern portfolio theory (MPT), and uncertainties in processing times. Traditionally, total completion time (TCT) and variance of completion times (VCT) are two KPIs for one-stage production scheduling, which relate to the first and second moments of completion times, respectively. We question whether the third moment of completion times is good to address the three challenges. In this paper, we introduce the skewness of completion times (SCT) in scheduling, and propose the ToB(a,b) heuristics for trade-off balancing. Through case studies with 5 levels of processing time uncertainties and compared to existing ToB(α) heuristics which balance trade-offs between TCT and VCT, we show that our ToB(a,b) heuristics dominate ToB(α) heuristics in terms of smaller expected values (E) of weighted sum of deviations from the best solutions of KPIs and smaller risks (σ) associated with these KPI deviations. Therefore, our ToB(a,b) heuristics are more robust to balance trade-offs between the three KPIs under processing time uncertainties.
| Original language | English |
|---|---|
| Pages (from-to) | 70-79 |
| Number of pages | 10 |
| Journal | Manufacturing Letters |
| Volume | 44 |
| DOIs | |
| State | Published - Aug 2025 |
Bibliographical note
Publisher Copyright:© 2025 The Author(s)
Funding
We appreciate support from the Department of Mechanical and Aerospace Engineering at University of Kentucky, the Natural Sciences and Engineering Research Council of Canada, and the Haskayne School of Business at University of Calgary.
| Funders |
|---|
| Department of Mechanical and Aerospace Engineering at University of Kentucky |
| Natural Sciences and Engineering Research Council of Canada |
| University of Calgary |
Keywords
- Key performance indicators
- Moments
- Robust scheduling
ASJC Scopus subject areas
- Mechanics of Materials
- Industrial and Manufacturing Engineering
Fingerprint
Dive into the research topics of 'Balancing trade-offs between first three moments of completion times for one-stage production'. Together they form a unique fingerprint.Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver