The Center will conduct a detailed distress survey of the entire project on an
annual basis or more frequently if deemed necessary by the Joint Evaluation Review
Team. This survey will document any observed distress included in the warranty
documents for the project. The IRI and rutting will be evaluated by the pavement
Management Branch within the Cabinet on an annual basis.
Annual ESAL'swill be calculated based on the MDT and vehicle classification counts
obtained by the Division of Planning. Aggregate ESALclass ESALfactors will be utilized
in conjunction with this data to calculate the annual ESAL's.
| Estado | Finalizado |
|---|---|
| Fecha de inicio/Fecha fin | 10/1/10 → 6/30/14 |
Financiación
- KY Transportation Cabinet: 75.000,00 US$