Cost investigation of battery-supercapacitor hybrid energy storage system for grid-connected hourly dispatching wave energy converter power

  • Pranoy Roy
  • , H. Bora Karayaka
  • , Jiang Biao He
  • , Yi Hsiang Yu

Producción científica: Articlerevisión exhaustiva

20 Citas (Scopus)

Resumen

This study demonstrates a successful application of a dispatching scheme for a slider-crank wave energy converter (WEC), utilizing a battery-supercapacitor hybrid energy storage system (HESS). The six sea states employed in the U.S. Department of Energy's Wave Energy Prize are incorporated to calculate the desired hourly grid reference power. The proposed architecture is responsible for fulfilling this grid demand in each dispatching period within an acceptable confidence level. A low pass filter is deployed to distribute the power between the supercapacitor and battery to exploit their benefits in the HESS configuration. Furthermore, several control techniques utilizing the supercapacitor state of charge (SOC) have been devised to predict the grid reference power accurately for each dispatching horizon. The techniques were applied to ensure that the energy storage system finishes each dispatching period with sufficient capacity for next-day operation (approximately 80 % SOC). The ESS life cycle expenditure is minimized based on three key factors: the best SOC algorithm, the best filter time constant, and the best depth of discharge (DOD) usage. The HESS was found to be the most cost-effective (2.6 ¢/kWh) for the WEC application under these conditions: a 100 ms filter time constant with a step-rules algorithm as a primary SOC controller, a 44 % DOD usage for the battery, and a 50 % DOD usage for the supercapacitor (SC). The HESS was also found to be less expensive than the battery-only (8.4 ¢/kWh) as well as the SC-only (2.8 ¢/kWh) cases. It is also noticeable that the SC calendar aging cost (61 %) and the battery cycling cost (96 %) contributed significantly to its overall HESS expenses for dispatching WEC power. Extensive MATLAB/Simulink simulations were performed to provide a realistic economic evaluation for WEC dispatching power.

Idioma originalEnglish
Número de artículo108347
PublicaciónJournal of Energy Storage
Volumen72
DOI
EstadoPublished - nov 25 2023

Nota bibliográfica

Publisher Copyright:
© 2023 Elsevier Ltd

Financiación

The authors would like to thank Dr. Robert Adams for his help with proofreading. This research did not receive any specific grant from funding agencies in the public, commercial, or not-for-profit sectors.

ODS de las Naciones Unidas

Este resultado contribuye a los siguientes Objetivos de Desarrollo Sostenible

  1. Affordable and clean energy
    Affordable and clean energy

ASJC Scopus subject areas

  • Renewable Energy, Sustainability and the Environment
  • Energy Engineering and Power Technology
  • Electrical and Electronic Engineering

Huella

Profundice en los temas de investigación de 'Cost investigation of battery-supercapacitor hybrid energy storage system for grid-connected hourly dispatching wave energy converter power'. En conjunto forman una huella única.

Citar esto